Categorical exclusion · example
San Carlos Hospital Community Microgrid
DOE would fund the San Carlos Apache Tribe to design and install a microgrid with a battery energy storage system, a 750 kW solar array and a controller. The PV array location changed from the earlier review: mostly rooftop, the rest ground-mounted.2
Facts from U.S. Department of Energy public records, each linked by number to its source; checked November 13, 2026. Section notes by ePlan.
At a glance
- Where
- SCA Healthcare Corporation campus in Peridot, Arizona. The battery and controller go on disturbed ground next to an existing building; most solar panels go on the logistics building roof, the rest in the south part of campus.2
- Size
- About 1 MW battery storage system and 750 kW solar PV array; the array is about one-fifth of the area of the original proposal.2
- Lead agency
- U.S. Department of Energy, Office of Energy Efficiency and Renewable Energy (NEPA Compliance Officer; Office of Indian Energy Policy and Programs)2
- Review
- Categorical exclusion, documented in a NEPA determination2
- Legal citation
- DOE categorical exclusions B4.14 (electrochemical-battery or flywheel energy storage systems) and B5.16 (solar photovoltaic systems), Appendix B to 10 CFR Part 10212
- Status
- NEPA determination signed February 11, 20262
Timeline
Documents U.S. Department of Energy published
What the documents say
CX-270928.pdf
- Rationale for determination
- Describes the microgrid at the Peridot campus, the revised mostly rooftop PV layout, Section 106 concurrence, USFWS no-effect finding, no wetlands or floodplain, and no significant impacts expected.2
- For Categorical Exclusion Determinations
- States the project fits Appendix B classes, has no extraordinary circumstances, was not segmented, and is categorically excluded from further NEPA review.2
- NEPA Provision
- Final determination requires an agreement condition to stop work and notify the Historic Preservation Office and DOE Project Officer if archaeological materials are found.2
Start one like it.
A project like San Carlos Hospital Community Microgrid? Describe yours and ePlan drafts the categorical exclusion memo (or short EA) in the agency's format. Where will the project happen?
More examples
- Chicago Libraries Solar Power, Chicago and West ChicagoCategorical exclusion · Determination review completed June 10, 2026
- Eugene Alderwood No. 1 115-kV Rebuild and Upgrades, Lane CountyCategorical exclusion · Estimated completion October 2028
- Carriger Solar Interconnection, Klickitat CountyCategorical exclusion · Record posted July 27, 2026
- Piccadilly Flats, City of PortlandCategorical exclusion subject to 24 CFR 50.4 · Review certified October 27, 2026
NEPA Categorical Exclusion Memo · All Federal NEPA projects
Sources
- DOE NEPA categorical exclusion determination pageenergy.gov
- CX-270928.pdfenergy.gov