Categorical exclusion · example
Chicago Libraries Solar Power
DOE would administer Congressionally Directed Spending to the City of Chicago to install rooftop solar PV systems up to 300kW and make energy conservation upgrades (HVAC retrofits, LED lighting) at city-owned public libraries.1
Facts from U.S. Department of Energy public records, each linked by number to its source; checked November 13, 2026. Section notes by ePlan.
At a glance
- Where
- City-owned library buildings: Thurgood Marshall Library (7506 S Racine Ave, Chicago, IL), West Chicago Library (118 W Washington St, West Chicago, IL) and Northtown Library (6800 N Western Ave, Chicago, IL).2
- Size
- Rooftop solar PV systems up to 300kW at the library buildings2
- Lead agency
- U.S. Department of Energy, Office of Energy Efficiency and Renewable Energy (Solar Energy Technologies Office); decided by the NEPA Compliance Officer2
- Review
- Categorical exclusion, documented in a NEPA determination signed by the NEPA Compliance Officer2
- Legal citation
- DOE categorical exclusions B5.1 (actions to conserve energy or water) and B5.16 (solar photovoltaic systems), Appendix B to 10 CFR Part 10212
- Status
- Final NEPA determination signed June 10, 20262
Timeline
- Determination review completed2
Documents U.S. Department of Energy published
What the documents say
CX-271041.pdf
- CX, EA, EIS Appendix and Number
- Cites categorical exclusions B5.1 for energy conservation actions such as efficient lighting and HVAC, and B5.16 for solar PV on buildings or in previously disturbed areas.2
- Rationale for determination
- Describes rooftop PV up to 300kW, HVAC and LED retrofits at three city-owned libraries, no ground disturbance, no change in facility use, and no anticipated impacts to resources.2
- NEPA Provision
- States that DOE has made a final NEPA determination, with review by the Solar Energy Technologies Office completed on 6/10/2026.2
- For Categorical Exclusion Determinations
- Finds no extraordinary circumstances, no segmentation of the action, and that the project is categorically excluded from further NEPA review.2
- Field Office Manager Determination
- Provides check boxes for whether Field Office Manager review is required, with no concurrence signature or date entered.2
Start one like it.
A project like Chicago Libraries Solar Power? Describe yours and ePlan drafts the categorical exclusion memo (or short EA) in the agency's format. Where will the project happen?
More examples
- San Carlos Hospital Community Microgrid, PeridotCategorical exclusion · NEPA determination signed February 11, 2026
- Eugene Alderwood No. 1 115-kV Rebuild and Upgrades, Lane CountyCategorical exclusion · Estimated completion October 2028
- Carriger Solar Interconnection, Klickitat CountyCategorical exclusion · Record posted July 27, 2026
- Piccadilly Flats, City of PortlandCategorical exclusion subject to 24 CFR 50.4 · Review certified October 27, 2026
NEPA Categorical Exclusion Memo · All Federal NEPA projects
Sources
- DOE NEPA categorical exclusion determination pageenergy.gov
- CX-271041.pdfenergy.gov