Environmental impact statement examples: how long did recent EISs take?
From 534 to 1,271 days, counted from the notice of intent (NOI) in the Federal Register to the final EIS, for the twelve below, filed June 2025 to September 2026. Each project's source is its EPA record, with the EIS PDFs[7].
We picked them for range, not as typical cases. Of all 142 EIS NOIs published June 2023 to September 2024, 64 (45.1%) reached a final EIS within the two years NEPA now allows, and 38 had filed nothing with EPA by September 30, 2026[8][7]. More on the NEPA timeline.
| Project | Lead agency | Final EIS | NOI to final | Within 2 years |
|---|---|---|---|---|
| Kemmerer Power Station Unit 1, Wyoming[9] | Nuclear Regulatory Commission | November 28, 2025 | 534 days | Yes |
| Mokelumne Amador Calaveras Forest Resilience, California[10] | Forest Service | April 17, 2026 | 568 days | Yes |
| Northfield Mountain pumped storage relicensing, Massachusetts, New Hampshire, Vermont[11] | FERC | February 6, 2026 | 605 days | Yes |
| Bull Mountains Mine No. 1 Amendment 3, Montana[12] | Office of Surface Mining | June 20, 2025 | 683 days | Yes |
| Hawaii-California Training and Testing[13] | Navy | November 21, 2025 | 707 days | Yes |
| Austin Light Rail Phase 1, Texas[14] | FTA | January 16, 2026 | 728 days | Yes, with 3 days to spare |
| Clarke County Water Supply, Iowa[15] | Natural Resources Conservation Service | April 10, 2026 | 735 days | No, by 5 days |
| F-35A training unit, Kingsley Field, Oregon[16] | Air Force | September 25, 2026 | 843 days | No |
| Cape Cod Bridges Program, Massachusetts[17] | FHWA | August 7, 2026 | 890 days | No |
| Post-2026 Lake Powell and Lake Mead guidelines, seven states[18] | Bureau of Reclamation | July 31, 2026 | 1,141 days | No |
| Bonanza Solar, Nevada[19] | BLM | August 21, 2026 | 1,173 days | No |
| Enbridge Line 5 Tunnel, Michigan[20] | Army Corps of Engineers | February 6, 2026 | 1,271 days | No; NOI in 2022, before the 2023 limit |
Environmental assessment examples with a FONSI
One EA, start to finish: the Forest Service's Caldor Fire Restoration Project on the Eldorado National Forest. Scoping opened May 17, 2023, the draft EA went out for comment August 28, 2024, and the first decision was signed March 25, 2025[21]. Our catalog page holds its scoping letter, draft and final EA, maps and decision notices.
More in our catalog: French Fire Restoration, North Fork Forest Recovery and Laguna Mountain Forest Restoration. Elsewhere, read each EA with its FONSI:
Categorical exclusion examples: decision memos and CE records
The Forest Service's decision memo for rebuilding 17 miles of the Virginia Creeper Trail after Hurricane Helene was signed February 21, 2025[3], under a category now at 7 CFR 1b.4(d)(26)[29]. Twelve more, one per category, are under decision memo examples.
A fuels CE took about seven months: the Tahoe National Forest's Russell Valley Fuels Reduction, under the wildfire resilience CE, went from scoping on September 13, 2024 to a signed decision memo on April 24, 2025[30].
NEPA examples: how to pick a precedent for your project
Take structure and issues from a precedent, not findings. Rank by: