What is NEPA scoping?
DOE defines scoping as the process, internal or public, to identify the scope of the NEPA review[4]. Under USDA's procedures, scoping for an EIS identifies the substantive issues and sets aside non-substantive issues and alternatives that are not technically or economically feasible or do not meet the purpose and need[1].
An agency that scopes can invite comment, hold scoping meetings or publish scoping information[1]; DOE says early scoping should be driven by the need to begin the review promptly[4]. A scoping letter is the written invitation.
Public scoping for an EA
With CEQ's government-wide rules removed in 2025[5], each agency's procedures set the details[6]. USDA treats a notice of intent for an EA as the exception, for national, regional or otherwise complex proposals, and leaves public comment to the responsible official[7]. DOE may publish a notice requesting scoping comments on an EA[4].
Scoping letter examples from 2025 and 2026
Eight real scoping letters and notices from the Forest Service, BLM, the National Park Service and Caltrans, sent from November 2025 to September 2026. Each names the expected level of review and gives a window for comments; each row cites the project page or notice.
| Agency | Project | Date | Review | Comment period |
|---|---|---|---|---|
| BLM, Siuslaw Field Office, Oregon | Thirty-Six Divide Thinning: a 5,800-acre planning area in Lane County[8] | Sep 23, 2026 | EA | 20 days |
| BLM, Utah and Nevada field offices | Silver Rock Transmission Line: about 330 miles, up to 600 kV; notice of intent[9] | Sep 3, 2026 | EIS | 30 days |
| National Park Service, George Washington Memorial Parkway | Vista Management Plan[10] | Mar 12, 2026 | EA | 30 days |
| Forest Service, Rogue River-Siskiyou National Forest | Moon Fire Recovery: removing fire-killed trees along forest roads[11] | Feb 25, 2026 | EA, emergency procedures | 23 days |
| Forest Service, Finger Lakes National Forest | Finger Lakes Trail re-route: a safer trailhead and a 0.1-mile connector[12] | Feb 3, 2026 | CE | 17 days |
| BLM Idaho Falls District and Caribou-Targhee National Forest | Dry Ridge Extension Exploration: phosphate drilling with up to 400 acres of disturbance[13] | Jan 23, 2026 | EA | 30 days |
| Forest Service, Shawnee National Forest | Ameren Merlot-Grand Tower transmission line rebuild, sent with a draft decision memo[14] | Dec 4, 2025 | CE | 21 days |
| Caltrans District 5, for FHWA under NEPA assignment | State Route 25, Hollister to Gilroy: revised notice of preparation and scoping[15] | Nov 5, 2025 | EIR/EA (CEQA and NEPA) | 44 days |
How long is a scoping comment period?
NEPA sets no length. It requires only that an EIS notice of intent request public comment[2], and USDA calls scoping a step with no prescribed process[1]. Where the Forest Service's objection rules apply, the legal notice for an EA opens a 30-day comment period that can't be extended, and a draft EIS gets at least 45 days[3][16].
The letters above gave 17 to 44 days: 17 and 21 for the two CEs, 20 to 30 for EAs, 30 for the EIS notice of intent and 44 for Caltrans' joint CEQA and NEPA review. CEQA's counterpart for an EIR is the notice of preparation: responsible and trustee agencies have 30 days to say what the EIR must cover[17][18].