Step 1: does NEPA apply?
An agency needs no environmental document if the action is not a final agency action, is excluded by a categorical exclusion or another law, would clearly and fundamentally conflict with another law, or is nondiscretionary[2]. A non-federal project with no or minimal federal funding is not a major federal action[6]; it may still need state review, such as Massachusetts MEPA or Hawaii HEPA.
Step 2: choose the level of NEPA review
If a categorical exclusion applies, the agency applies it and documents the decision where its procedures call for that[3]. Otherwise it prepares an environmental assessment when a significant effect is not reasonably foreseeable or its significance is unknown, and an environmental impact statement when one is[2].
How long does a NEPA review take?
Historically, longer than the law now allows. Forest Service decisions signed 2005 to 2021 took a median 441 days for an EA and 1,041 days for an EIS; 59% of EAs and 92% of EISs took over a year[5]. Since 2023 an EA gets one year and an EIS two, counted from the level-of-review decision or the notice of intent[7][4]. See the NEPA timeline.
Since July 4, 2025, a project sponsor may pay 125 percent of the anticipated cost to have an EA completed within 180 days of payment, or an EIS within one year of the notice of intent[8].
Where NEPA procedures live now
With CEQ's regulations removed in 2025[9], each agency follows its own NEPA procedures, indexed by CEQ on nepa.gov[10]. Recent examples:
- USDA, including the Forest Service: 7 CFR part 1b, final rule April 3, 2026[11]
- Interior: 43 CFR part 46 plus a Departmental Handbook, final rule February 24, 2026[12]
- Energy: 10 CFR part 1021 plus DOE's NEPA Implementing Procedures, revised July 13, 2026[13]
- FHWA, FRA and FTA: 23 CFR part 771, final rule September 1, 2026[14]
- FAA: Order 1050.1G[15]; FEMA: DHS Instruction Manual 023-01-001-01[16]; HUD grantees: 24 CFR Part 58[17]