Stormwater pollution prevention plan · example
Lindsay Project 1
A construction stormwater pollution prevention plan for the Lindsay Project 1 site development near 8326 172nd St NE, Arlington. It sets erosion, sediment and pollutant controls under 13 elements of the Western Washington stormwater manual.1
Facts from City of Arlington public records, each linked by number to its source; checked November 13, 2026. Section notes by ePlan.
At a glance
- Where
- 8326 172nd St NE, Arlington, Washington 98223; Quilceda Creek basin, Snohomish watershed, WRIA 7; Section 25, 26, Township 31 N, Range 5 W.1
- Size
- 32.26-acre site, with 29.43 acres of disturbance and 12.17 acres of new impervious area.1
- Lead agency
- City of Arlington1
- Review
- Stormwater pollution prevention plan, prepared as part of a Stormwater Site Plan1
- Legal citation
- Minimum Requirement 2 of the Stormwater Management Manual for Western Washington1
- Status
- SWPPP prepared February 2026 for the permit application1
Timeline
- SWPPP prepared1
Documents City of Arlington published
What the documents say
20260210 PJ26-0104 SWPPP
- 3.1.1 Project Data Summary
- Lists applicant MJS Investors, parcels, Quilceda Creek basin, a 32.26-acre site, 29.43 acres of disturbance, no existing impervious area and 12.17 acres proposed.1
- 3.2 Introduction
- States the SWPPP meets Minimum Requirement 2, covers conceptual construction activities, and aims to prevent erosion, sedimentation and water quality violations through BMPs.1
- 3.2.1 Element 1: Preserve Vegetation/Mark Clearing Limits
- Calls for minimizing tree removal and soil compaction, retaining duff and native topsoil, and lists BMP C101 for preserving natural vegetation.1
Start one like it.
A project like Lindsay Project 1? Describe yours and ePlan drafts the stormwater pollution prevention plan. Where is the construction site?
SWPPP · All Construction projects