Environmental assessment · example
Laguna Mountains Forest Restoration
Forest and meadow restoration across 9,343 acres of the 13,129-acre Laguna Mountain Plateau over several years, to restore fire-adapted processes, improve forest health and resilience, and repair degraded meadow and watershed conditions.2
Facts from USDA Forest Service public records, each linked by number to its source; checked November 13, 2026. Section notes by ePlan.
At a glance
- Where
- Laguna Mountain Plateau, Descanso Ranger District, east of Descanso and north of Interstate 8, San Diego County, California1
- Size
- 9,343 acres of treatment within a 13,129-acre project area2
- Lead agency
- USDA Forest Service, Cleveland National Forest, Descanso Ranger District1
- Review
- Environmental assessment, draft EA released for 30-day comment2
- Legal citation
- 36 CFR 218.7 (objection process); 36 CFR 218.8(c)2
- Status
- Draft EA out for 30-day comment, notice letter dated August 27, 20262
Timeline
Documents USDA Forest Service published
- PDFDRAFT-USDA-EA-Laguna Project 508cPosted August 27, 2026
- PDFAppendix B References CitedPosted August 27, 2026
- PDFAppendix A Design Features and Mitigation MeasuresPosted August 27, 2026
- PDF2026.08.28 Laguna Legal AdPosted August 27, 2026
- PDFLaguna letter 30 day notice and commentPosted August 27, 2026
- PDFLaguna Mtns Forest Restoration Scoping LetterPosted April 2, 2026
- PDFLaguna Mtns Forest Restoration Project DescriptionPosted April 1, 2026
What the documents say
Laguna Mtns Forest Restoration Project Description
- Project Setting
- Project covers 13,129 acres of the Laguna Mountain Plateau at 5,000-6,100 feet, with 8,413 acres of montane forest, 983 of meadow and 79 of chaparral proposed for treatment.4
- Purpose and Need
- Fire suppression has left forests dense and at risk of stand-replacing fire; the 2003 Cedar and 2013 Chariot fires destroyed nearly 23 percent of mature canopy, and meadows need restoration.4
Laguna letter 30 day notice and comment
- How to Comment and Timeframe
- Comments are open for 30 days after the legal notice appears in the San Diego Union Tribune, and only timely specific comments give standing to object.2
Laguna Mtns Forest Restoration Scoping Letter
- Summary of Proposed Action
- Proposes thinning, reforestation, low-intensity prescribed fire, fuelbreaks, and meadow work including check dam removal, gully repair and a Chico-Gatos Connector Trail reroute.3
Start one like it.
A project like Laguna Mountains Forest Restoration? Describe yours and ePlan drafts the scoping letter. Which national forest is the project on?
More examples
- Mosquito Fire Restoration, Tahoe National ForestEnvironmental assessment · Expected decision November 2026
- Tahoe National Forest E-Bike Trail DesignationEnvironmental assessment · Finding/Decision Date September 23, 2026
- Mokelumne Amador Calaveras Forest Resilience Project, Eldorado and Stanislaus National ForestsEnvironmental impact statement · FEIS NOA in Federal Register April 17, 2026
- Community Protection - Eastside, Plumas National ForestEnvironmental assessment · Decision signed December 23, 2025
Forest Service NEPA · All Forest Service projects
Sources
- Laguna Mountain Forest Restoration: Forest Service project pagefs.usda.gov
- Laguna letter 30 day notice and commentusfs-public.app.box.com
- Laguna Mtns Forest Restoration Scoping Letterusfs-public.app.box.com
- Laguna Mtns Forest Restoration Project Descriptionusfs-public.app.box.com