Contractors and owners demolishing or gutting buildings

Where is the building being demolished or renovated?

Free check of the EPA asbestos notice for demolition and renovation: when you must file, the 10-working-day lead time and what you need first.

  • Free to read
  • No sign-up until the draft
  • Hands off to the right door
BUILDINGWORK AREASTOREEXIT

ePlan fills in

  • Parcel
  • Year built
  • Building outline
  • Aerial view

How it works

Asbestos NESHAP notice checklist, from one answer

  1. Enter the address, the work and the amounts your asbestos survey found.
  2. ePlan checks whether full rules or notice only apply and counts 10 working days back from your start date.
  3. Read the checklist free. Need dust control for the demolition? Start a dust control plan.

What you get

Asbestos NESHAP notice checklist and 1 more document

The check is free. The paperwork after it is drafted at the Grading and erosion control plan door.

The first draft

Asbestos NESHAP notice checklist (free)

  1. Inspection before any work
  2. Demolition or renovation
  3. Regulated asbestos amounts
  4. Notice timing and updates
  5. Removal and wetting work practices
  6. Waste handling and disposal

Modeled on: 40 CFR 61.145 and your state or local agency's demolition and renovation notification form

Next · 2

Dust control plan for the demolition

  1. Site and disturbed area
  2. Dust sources
  3. Controls
  4. Inspections and records

From public data

What ePlan fills in, and from where

10 working days

is the minimum notice before asbestos removal or a demolition begins
Source: 40 CFR 61.145(b)(3), eCFR

Ready for the paperwork?

Draft the erosion and sediment control plan, grading narrative and dust control plan your city or county wants with the grading permit. Free to read.

Grading and erosion control plan →

Questions

Asbestos NESHAP Demolition Notification: what people ask

Do I need to file if there's no asbestos?

For a demolition, yes. The notification requirements still apply when the regulated asbestos is below the thresholds or there is none. A renovation needs notice only when the asbestos to be disturbed meets the thresholds.

Source: ecfr.gov

What amounts trigger the full rules?

At least 260 linear feet on pipes, 160 square feet on other facility components, or 35 cubic feet off facility components where the length or area couldn't be measured. Below those, EPA's rule doesn't require the removal work practices.

Source: epa.gov

Who inspects the building?

The owner or operator must have the affected part of the building thoroughly inspected for asbestos before demolition or renovation starts. That inspection is fieldwork by an inspector; ePlan can't do it, but drafts the notice from the survey results.

Source: ecfr.gov