Free plan BIOZ check for Polish building sites: the 30-day, 20-worker and 500 person-day tests, listed high-risk works and who prepares it.

  • Free to read
  • No sign-up until the draft
  • Hands off to the right door
BUILDINGWORK AREASTOREEXIT

ePlan fills in

  • Parcel (Geoportal)
  • Building permit record
  • Size test
  • High-risk works

How it works

Plan BIOZ check, from one answer

  1. Enter the site and describe the job's size and works.
  2. ePlan checks whether a plan BIOZ is required and what it must address.
  3. Read the free check. Working on a site in Italy too? Start a POS draft.

What you get

Plan BIOZ check and 2 more documents

The check is free. The paperwork after it is drafted at the POS door.

The first draft

Plan BIOZ check (free)

  1. Site, investor and site manager
  2. Size test: 30 working days and 20 workers, or 500 person-days
  3. High-risk works on the statutory list
  4. Designer's BIOZ information
  5. What the plan must address for each risky work
  6. Who prepares it and when

Modeled on: Prawo budowlane, art. 20 and 21a (Dz.U. 2026 poz. 524)

Next · 2

IBWR outline (instrukcja bezpiecznego wykonywania robót)

  1. Work and sequence
  2. Hazards
  3. Safe methods
Next · 3

POS for an Italian site (paid draft)

  1. Company and site roles
  2. Tasks and equipment
  3. Risks and measures

From public data

What ePlan fills in, and from where

500 person-days

or over 30 working days with at least 20 workers at once means the site needs a plan BIOZ
Source: Prawo budowlane, art. 21a ust. 1a (Dz.U. 2026 poz. 524)

Ready for the paperwork?

Draft the POS for one firm on one site from the coordinator's PSC and your crew, trade and tools. For Italian contractors and trades. Free to read.

POS →

Questions

Plan BIOZ: what people ask

When is a plan BIOZ required?

When the works will last over 30 working days with at least 20 workers employed at once, or the planned work exceeds 500 person-days. It is also required whenever works from the statutory high-risk list take place.

Source: eli.gov.pl

Who prepares the plan BIOZ?

The kierownik budowy (site manager) prepares it, or makes sure it is prepared, before construction starts. It is based on the BIOZ information that the designer prepares as part of the design.

Source: eli.gov.pl

Which works are on the high-risk list?

Among others: risk of burial or falling from height, chemical or biological hazards, ionising radiation, work near high-voltage lines or active traffic, risk of drowning, wells, underground work and tunnels, caissons, explosives, and installing or dismantling heavy prefabricated elements.

Source: eli.gov.pl