Crane firms, contractors and tower builders near airports

Where will the crane or structure stand?

Free check of the 14 CFR Part 77 notice rules for cranes, towers and buildings near airports, plus a 7460-1 worksheet. Filing with the FAA is free.

  • Free to read
  • No sign-up until the draft
  • Hands off to the right door
BUILDINGWORK AREASTOREEXIT

ePlan fills in

  • Nearest airports and runways
  • Ground elevation
  • Distance to runway
  • Notice threshold

How it works

Part 77 notice check and Form 7460-1 worksheet, from one answer

  1. Enter the location, the height and the start date.
  2. ePlan finds nearby runways, tests the Part 77 notice rules and fills a 7460-1 worksheet.
  3. Building with federal money or a federal permit? Start a NEPA categorical exclusion memo.

What you get

Part 77 notice check and Form 7460-1 worksheet and 1 more document

The check is free. The paperwork after it is drafted at the Categorical exclusion memo (or short EA) in the agency's format door.

The first draft

Part 77 notice check and Form 7460-1 worksheet (free)

  1. Structure location and coordinates
  2. Ground elevation and height above ground
  3. Nearest runway and distance
  4. Notice criteria tested (14 CFR 77.9)
  5. Work dates and duration
  6. Form 7460-1 fields ready to enter in OE/AAA
Next · 2

NEPA categorical exclusion memo

  1. Project description
  2. Categorical exclusion relied on
  3. Extraordinary circumstances review
  4. Determination

From public data

What ePlan fills in, and from where

200 feet

above ground is the height at which any construction needs FAA notice on Form 7460-1, near an airport or not
Source: 14 CFR 77.9(a), eCFR

Ready for the paperwork?

Draft a NEPA categorical exclusion memo or short environmental assessment for a federally funded project, in the agency's format. Free to read.

Categorical exclusion memo (or short EA) in the agency's format →

Questions

FAA Form 7460-1: what people ask

When do I need to file a 7460-1?

When construction will be more than 200 feet above ground, or would rise above an imaginary surface around a public airport: a 100:1 slope out to 20,000 feet from runways over 3,200 feet, 50:1 out to 10,000 feet for shorter runways, or 25:1 out to 5,000 feet from heliports.

Source: ecfr.gov

How far ahead must I file?

At least 45 days before construction starts, or before you apply for a construction permit, whichever comes first. If the structure also needs an FCC license, file with the FAA on or before the date you apply to the FCC.

Source: ecfr.gov

Does a tower also need FCC registration?

Yes, if it needs FAA notice because it is a physical obstruction. The owner of any antenna structure that requires notice to the FAA must register it with the FCC.

Source: ecfr.gov