Contractors pumping water from trenches and excavations

Where is the excavation?

Free dewatering plan checklist for pumping trenches and excavations on a construction site: controls, daily checks and records. Local permits may apply.

  • Free to read
  • No sign-up until the draft
  • Hands off to the right door
A HORIZON · LOAMB · SANDY LOAM · PERC 24 MIN/INSEASONAL HIGH WATER · 54 IN 1,000 GAL

ePlan fills in

  • Groundwater levels
  • Receiving water
  • Impaired water

How it works

Dewatering plan checklist, from one answer

  1. Pin the site and say where the water will go.
  2. ePlan finds the receiving water and lists controls and daily checks. Your city or state may need its own discharge permit.
  3. Read the free checklist. Need the whole site plan? Start a SWPPP draft.

What you get

Dewatering plan checklist and 1 more document

The check is free. The paperwork after it is drafted at the SWPPP door.

The first draft

Dewatering plan checklist (free)

  1. Excavation and expected flow
  2. Discharge point and receiving water
  3. Treatment controls
  4. Daily inspection while discharging
  5. Records: times, rate, sediment or sheen, photos
  6. Corrective actions
Next · 2

Construction SWPPP

  1. Site and receiving water
  2. Erosion and sediment controls
  3. Inspections

From public data

What ePlan fills in, and from where

Every day

that a dewatering discharge occurs, EPA's construction permit requires an inspection of the dewatering controls
Source: EPA 2022 Construction General Permit, Part 4.3.2

Ready for the paperwork?

Disturbing an acre or more? Answer four questions and get a site-specific SWPPP draft with BMPs, an inspection form and NOI notes. Free to read.

SWPPP →

Questions

Dewatering Plan: what people ask

Can I pump excavation water off a construction site?

Only with controls. Federal effluent guidelines prohibit discharges from dewatering, including trenches and excavations, unless they are managed by appropriate controls.

Source: ecfr.gov

How often must dewatering be inspected?

Under EPA's 2022 Construction General Permit, once per day on which the dewatering discharge occurs. State permits may differ.

Source: epa.gov

What goes in the dewatering record?

Within 24 hours: the date, inspectors, approximate start and end times, estimated rate in gallons per day, any sediment plume, unusual color, odor, foam or sheen, and photos of the water before and after treatment and of the discharge point.

Source: epa.gov