Interconnection queue status digest (free)
- Project, queue ID and point of interconnection
- Current phase and cluster
- Posted study dates
- Deposits and readiness milestones
- Changes since the last posting
- Other requests at the same substation
Solar, storage and wind developers with a project in a queue
Free tracker for your generator interconnection request: queue position, study phase and posted dates, read from your grid operator's own queue file.
ePlan fills in
How it works
What you get
The check is free. The paperwork after it is drafted at the NEPA environmental assessment door.
From public data
were waiting in US interconnection queues by 2022, up from 1,400 GW a year earlier, as average waits grew from about 4 to 5 years
Source: FERC Order No. 2023, 88 FR 61014
Draft a NEPA environmental assessment and FONSI, or an EIS outline, that follows a reference document. Free to read; every unconfirmed fact is marked.
Questions
It replaced the serial queue with a first-ready, first-served cluster study process. Developers pay study and commercial readiness deposits, show site control when they apply, and face withdrawal penalties. Each transmission provider had to adopt a transition process to the new rules.
Order No. 2023 added study delay penalties measured against the tariff deadline: $1,000 per business day for a late cluster study, $2,000 for a late cluster restudy or affected system study, and $2,500 for a late facilities study.
Under the pro forma rules in Order No. 2023: a $5,000 application fee plus a study deposit of $35,000 plus $1,000 per MW for 20 to 80 MW, $150,000 for 80 to 200 MW, or $250,000 for 200 MW or more. Your operator's tariff may differ.
Related doors
What are you proposing, and where?
Where is the project site?
Which HUD-funded project is it?
Which map file do you need converted?
Where is your principal office?
Which Forest Service CE fits your project?
Answer it and ePlan opens the NEPA environmental assessment door, which drafts the paperwork.