Applicants told they need a state environmental form

Where is the site?

Free finder: which state environmental form your project needs (CEQA, SEPA, SEQR or MEPA), who fills which part, and the first deadlines.

  • Free to read
  • No sign-up until the draft
  • Hands off to the right door
5 FT APN 018-224-07 ADU · 640 SQ FT

ePlan fills in

  • State and lead agency
  • Parcel
  • Wetlands
  • Flood zone
  • Listed species

How it works

State environmental review route memo, from one answer

  1. Pick the state and enter the site.
  2. ePlan names the form, who fills it and the first deadlines.
  3. Read the route memo free. Federal agency involved? Start a NEPA categorical exclusion memo.

What you get

State environmental review route memo and 1 more document

The check is free. The paperwork after it is drafted at the Categorical exclusion memo (or short EA) in the agency's format door.

The first draft

State environmental review route memo (free)

  1. Your project and state
  2. Which law and form applies
  3. Who fills which part
  4. First deadlines
  5. Map facts for the form
  6. Federal NEPA overlap
Next · 2

NEPA categorical exclusion memo

  1. Proposed action
  2. Categorical exclusion relied on
  3. Extraordinary circumstances
  4. Determination

From public data

What ePlan fills in, and from where

20 calendar days

is how long a New York lead agency has to decide significance after receiving the application, EAF and any needed information
Source: 6 NYCRR 617.6(b)

Ready for the paperwork?

Draft a NEPA categorical exclusion memo or short environmental assessment for a federally funded project, in the agency's format. Free to read.

Categorical exclusion memo (or short EA) in the agency's format →

Questions

State Environmental Review Finder: what people ask

Who fills out a SEQR EAF?

In New York the applicant or project sponsor completes Part 1; the lead agency completes Parts 2 and 3.

Source: dec.ny.gov

Who prepares a SEPA checklist?

In Washington the lead agency either prepares the checklist or requires the applicant to prepare it.

Source: app.leg.wa.gov

What goes in a CEQA initial study?

In brief form: the project and its location, the environmental setting, a checklist of effects with short explanations, ways to mitigate significant effects, a check against zoning and plans, and the names of the preparers.

Source: law.cornell.edu

The rules this door follows