Landowners, farms and water districts adding small hydro

Where would the turbine take its water?

Free check of which FERC path fits your micro hydro: a qualifying conduit notice, the small hydro exemption, or a declaration for a stream.

  • Free to read
  • No sign-up until the draft
  • Hands off to the right door
WETLAND · 0.6 AC (NWI) CROSSING · 24 IN CULVERT HUC-12 180201250701

ePlan fills in

  • Stream or canal
  • Watershed and flows
  • Elevation drop (head)
  • Federal land
  • Wetlands

How it works

Micro hydro permit path check, from one answer

  1. Enter the water source, head and flow, and whether you'll tie to the grid.
  2. ePlan maps the stream or canal and checks the conduit, exemption and declaration paths.
  3. Placing fill in a stream for the intake? Start a nationwide permit PCN draft.

What you get

Micro hydro permit path check and 2 more documents

The check is free. The paperwork after it is drafted at the Pre-Construction Notification door.

The first draft

Micro hydro permit path check (free)

  1. Site, water source and owner
  2. Head, flow and capacity
  3. Qualifying conduit test
  4. Small hydro exemption or declaration of intention
  5. State water right questions
  6. Stream work that needs a Corps permit
Next · 2

FERC notice of intent for a qualifying conduit (18 CFR 4.401)

  1. Introductory statement
  2. Non-federal conduit and its water use
  3. Not licensed or exempted on or before Aug 9, 2013
  4. Project drawings
  5. Verification
Next · 3

Nationwide Permit 17 pre-construction notification

  1. Project and FERC authorization
  2. Fill in streams or wetlands
  3. Avoidance and minimization
  4. Species and historic properties

From public data

What ePlan fills in, and from where

15 days

is how long FERC has to make an initial call on a qualifying conduit notice; if no one contests it within 30 days of public notice, it qualifies
Source: 16 U.S.C. 823a(a)(2)

Ready for the paperwork?

Draft the Army Corps pre-construction notification (ENG Form 6082) for a dock, bank repair or small crossing. Wetlands and species checked. Free to read.

Pre-Construction Notification →

Questions

Micro Hydro Permit Check: what people ask

Does small hydro on an irrigation canal need a FERC license?

Often not. A qualifying conduit facility, up to 40 MW using a non-federal canal, pipeline or ditch built for farm, city or industrial water, files a notice of intent instead. FERC makes an initial determination within 15 days; if no one contests within 30 days of public notice, it qualifies.

Source: law.cornell.edu

What goes in the notice of intent?

An introductory statement in FERC's format, a statement that the project uses a non-federally owned conduit, a statement that it wasn't licensed or exempted on or before August 9, 2013, project drawings, any preliminary permit number, and a verification.

Source: ecfr.gov

Do I need an Army Corps permit too?

If you place fill in a stream or wetland, likely. Nationwide Permit 17 covers fill for hydropower projects under 10,000 kW at existing reservoirs licensed by FERC, or with a FERC exemption, and needs a pre-construction notification. The 2026 nationwide permits run to March 15, 2031.

Source: govinfo.gov

The rules this door follows